Wreck Pond Outfall,

Spring Lake, NJ

Project Challenges:

  • Working through the winter on the Jersey Shore
  • Groundwater
  • Working with tide
  • Coordination with wildlife and plant restrictions

Work Performed:

Simpson & Brown was contracted to install 600 l.f. of precast concrete box culvert to connect Wreck Pond to the Atlantic Ocean. The culvert would facilitate drainage as well as provide a path for fish to travel. The Box Culvert was supported by timber piles and a combination of timber and steel supports. The work was conducted 13’ below grade on the beach which required steel sheeting to be utilized.

Project Details

Project Owner: Borough of Spring Lake

Project Client: Engineer-Avakian Engineering, Neptune, NJ

Project Cost: $1 million – $5 million

Project Duration: 6 months

Project Highlights