IMTT Ringwall Foundation
Project Details:
Project Owner: IMTT Inc.
Project Client: IMTT Inc.
Project Cost: Approx. $230,000
Project Duration: 2 Months
Project Challenges:
- Tight Work Area
- Coordination with Facility Operations for all work activities based upon Terminal Operations
- One of the RIngwalls was required to be constructed beneath a suspended tank
Work Performed:
- Excavation
- Formwork
- Reinforcing Steel
- Concrete Placement
- Backfill and Site Restoration
Project Photo Gallery: