Project Details:
Project Owner: IMTT Inc.
Project Client: IMTT Inc.
Project Cost: approx. $875,000
Project Duration: 4 months
Project Challenges:
- Active Terminal Facility
- Coordination with Daily Operations for allowable work to be performed
- Multiple below grade utilities altered design due to inability to shut down and reroute lines
Work Performed:
- Excavation
- Reinforcing Steel
- Concrete Placement
- Backfill and Site Restoration to Match Existing