Wildwood Substation
Project Details:
Project Owner: Atlantic City Electric
Project Client: Atlantic City Electric
Project Cost: $1 million – $5 million
Project Duration: 8 months
Project Challenges:
- Work took place in an active electrical substation
Work Preformed:
- Excavation
- Stelcor Piles
- Reinforcing Steel
- Structural Concrete Work
- Control Building – Masonry and Steel
- Excavation for Electrical Ductbanks
- Shoring of existing in place below grade electrical utilities