Liberty State Park

Project Challenges:

  • Timber fender demolition
  • Pile driving
  • Precast concrete caps and planks
  • Cast in place concrete
  • Timber fender
  • Timber piles

Work Performed:

Demolition of existing timber pier. Drove pipe piles in 2 pile bents in a radius shape from wide to narrow. Place precast concrete pile caps and precast concrete planks. Install cast in place deck over precast. Install decorative timber fender system to match historic look. Install 100 pile timber cluster at end of pier to match historic look.

Project Details

Project Owner: State of NJ Parks

Project Client: State of NJ Parks

Project Cost: $1 million – $5 million

Project Duration: 4 months

Project Highlights