Jersey Shore Medical Center

UG Utility Shoring

Project Challenges:

Drilled Soldier piles were installed within close proximity to existing buildings, along an active driveway and through an existing parking lot. All hospital activities remained in operation throughout the full duration of the project.

Work Performed:

Support of Excavation consisted of drilled mini-pile soldier piles with treated timber lagging with internal wales and braces to support the deep excavation.

Project Details

Project Owner: Jersey Shore Medical Center

Project Client: VA Spatz & Sons Construction, Inc.

Project Duration: 3 Months

Project Highlights

LET'S CONNECT