Project Challenges:

  • Tight schedule
  • Coordination of large amount of workers
  • Specialty equipment

Work Performed:

  • Field Measuring/Pre-Survey work
  • Removal of existing structural pier
  • Driven piles
  • Driven steel sheeting
  • Reinforced Concrete Work
  • Railing and Walkway Installation
  • Field Measuring/ Pre- Survey work
  • Removal of existing structural pier
  • Driven piles
  • Driven steel sheeting
  • Reinforced Concrete Work
  • Railing and Walkway Installation

Project Details

Project Owner: International Matex Tank Terminals

Project Client: International Matex Tank Terminals

Project Cost: $1 million – $5 million

Project Duration: 3 months

Project Highlights