Christiana Hospital

Women’s Wing Phase 1

Project Challenges:

Drilled Soldier piles were installed within 3 inches of the existing hospital wall. Hospital Emergency Room was required to remain active throughout the duration of the project.

Work Performed:

Support of Excavation consisted of drilled mini-pile soldier piles with treated timber lagging and drilled tiebacks to support an 18 l.f. cut from existing grade.

Project Details

Project Owner: Christiana Health Care System

Project Client: H.T. Sweeney & Son Inc.

Project Duration: 3 months

Project Highlights