Project Challenges:

Not only was the job site undeveloped, there was winter concrete and high amounts of rainfall. The challenges of the pandemic—working away from home, to be more precise—also was a consideration.

Work Performed:

Simpson & Brown performed excavation, form work, and rebar for various concrete footings, slabs, and equipment pads. Truck loading rack was 300+ yards poured with a pump truck in the winter using concrete additives and insulation.

Project Details

Project Owner: Buckeye partners LP

Project Client: FM Sylvan

Project Duration: between $2 to $3 million

Project Duration: 6 months

Project Highlights